Current:Home > MarketsMinnesota Groups Fear Environmental Shortcuts in Enbridge’s Plan to Rebuild Faulty Pipeline -Wealth Empowerment Zone
Minnesota Groups Fear Environmental Shortcuts in Enbridge’s Plan to Rebuild Faulty Pipeline
View
Date:2025-04-15 16:01:15
As part of a consent decree, Enbridge was told to replace its Line 3 segment in the United States, which runs almost entirely within Minnesota. And it set a deadline of Dec. 31, 2017. If the company fails to meet it, it will be required to provide extensive and costly safety measures to safeguard the old line.
But meeting the Justice Department’s deadline for replacing Line 3 is impossible. Minnesota officials haven’t agreed to permit the new pipeline, and that decision isn’t expected until fall 2017. The rigorous work required for the environmental impact statement won’t be done until after April 2018.
Work couldn’t be completed until 2019 at the earliest—long past the federal deadline.
Now, environmental groups fear that Enbridge is trying to fast-track the work before a thorough review is done, using the federal settlement as justification. They cite public comments by Enbridge officials and statements in filings with the Minnesota PUC.
The issue erupted during an open comment period on terms of the consent decree that ended last week. The Minnesota Center for Environmental Advocacy (MCEA) and Friends of the Headwaters have led the vocal opposition.
“The Department of Justice has no business ordering someone to build a tar sands pipeline through our state,” said Kevin Lee, an attorney for MCEA. “We see the urgency being expressed by Enbridge as a result of this proposed consent decree as a self-serving attempt to influence the permitting process that is the state’s power alone.”
Enbridge’s plan to spend $7.5 billion to replace and greatly increase the capacity of Line 3 is the most ambitious in its history. The project is part of its plans for a network of new and expanded pipelines that would carry tar sands into the U.S.
In an article in a North Dakota newspaper, Enbridge project manager Barry Simonson said, “We hope [the Justice Department consent decree] does instill a new sense of urgency at all levels of the [Minnesota] government, from the governor’s office down to the appropriate agencies underneath the governor and his staff.”
The company also cited the urgency of replacing Line 3 in a letter to the PUC opposing additional hearings on the new Line 3 project.
Michael Barnes, an Enbridge spokesman, reiterated the company’s position of pushing forward with the project as quickly as possible.
“Enbridge intends to continue engaging at all levels of government to seek expediency on approvals for Line 3’s replacement,” Barnes said. “We remain committed to following the state and federal processes and meeting all state and federal laws and regulations.”
The fight over this pipeline is yet another example of the unprecedented opposition to pipeline projects in which companies are being called ahead of time to address potential environmental damage if leaks were to occur.
In North Dakota, that opposition has brought thousands of protesters together to demonstrate against the construction of the Dakota Access pipeline, a $3.7 billion project that would ferry 470,000 barrels of crude oil a day from the Bakken oil fields 1,172 miles across four states.
A national spotlight has been focused on the project as the Standing Rock Sioux tribe has gained widespread support in its appeal that the pipeline could threaten their environmental and economic well-being, as well as destroy historic, religious, and cultural sites. The pipeline, being built by Texas-based Energy Transfer Partners, is more than half built already, complicating their plight.
In Minnesota, work is far from even getting started on a new Line 3. Enbridge has pushed its hopes to expedite the work, setting up the conflict with environmental groups during the recent public comment period on the consent decree.
The Justice Department did not respond to questions from InsideClimate News, though Lee said the agency has said the consent decree is not intended to interfere with the ongoing environmental review and permitting procedures in Minnesota.
Meanwhile, state officials have said they are not expediting anything.
In the wake of the court ruling a year ago, the Minnesota PUC directed a full environmental impact statement for the segment of new Line 3 that would cut diagonally through the state. The most stringent review that the state can require orders in-depth studies to examine possible harm to a number of environmental components, including water sources, wetlands and wildlife habitat.
Enbridge had argued that a full EIS was unnecessary because less intensive alternative environmental reviews were sufficient to satisfy Minnesota’s permitting process.
In a letter to the Justice Department, the Minnesota PUC cautioned that approval of new Line 3 is not a done deal.
“The Commission cannot at this time estimate when the need and route permit proceedings for New Line 3 will be completed, nor can it say whether Enbridge’s need and route applications for the construction of New Line 3 will be approved, modified, or rejected,” according to a letter by Dan Wolf, the PUC’s executive secretary, to the Justice Department.
Wolf said the state’s environmental review will proceed as scheduled and a final report will not be ready for consideration until sometime after April 2018.
“We respect and appreciate the process that was used to arrive at the consent decree, but as the regulatory body with the responsibility to grant or deny a route permit there is still the normal regulatory process that will be followed,” Wolf said in an interview with InsideClimate News.
The Justice Department will now review the comments to decide if any changes to the consent decree are warranted, including altering the Line 3 deadline, before seeking final approval of the deal in federal court.
Opponents are urging clarity from the department.
“The 2010 Kalamazoo oil spill was a devastating event that illustrates first and foremost the need to adequately understand the risks and impacts of pipeline spills before those risks are undertaken,” according to a letter to the U.S. Department of Justice from Kathryn M. Hoffman, interim legal director of the Minnesota Center for Environmental Advocacy.
“Should this Consent Decree be understood as bearing federal approval of an expedited environmental review and permitting process for the L3R Project, the document would effectively require the State of Minnesota to bear the risks of those spills without the benefit of adequate study and evaluation beforehand.”
Terms of the settlement, spelled out in a consent decree that still must be approved by a federal judge, include a $62 million fine and the requirement that Enbridge spend at least $110 million on a series of spill prevention safeguards and other improvements along nearly 2,000 miles of its pipeline system in the Great Lakes region.
veryGood! (41123)
Related
- FACT FOCUS: Inspector general’s Jan. 6 report misrepresented as proof of FBI setup
- Priscilla Presley Shares Why She Never Remarried After Elvis Presley's Death
- Law and order and the economy are focus of the British government’s King’s Speech
- What to know about Issue 1 in Ohio, the abortion access ballot measure, ahead of Election Day 2023
- Trump wants to turn the clock on daylight saving time
- Barbra Streisand details how her battle with stage fright dates back to experience in Funny Girl
- Teachers in Portland, Oregon, strike for a 4th day amid impasse with school district
- Rashida Tlaib defends pro-Palestinian video as rift among Michigan Democrats widens over war
- The White House is cracking down on overdraft fees
- Horoscopes Today, November 5, 2023
Ranking
- Breaking debut in Olympics raises question: Are breakers artists or athletes?
- Is your financial advisory company among the best? Help USA TODAY rank the top firms
- Voters in Pennsylvania to elect Philadelphia mayor, Allegheny County executive
- EU envoy in surprise visit to Kosovo to push for further steps in normalization talks with Serbia
- NCAA hands former Michigan coach Jim Harbaugh a 4-year show cause order for recruiting violations
- Beshear hopes abortion debate will help him win another term as governor in GOP-leaning Kentucky
- Horoscopes Today, November 6, 2023
- Japan and UK ministers are to discuss further deepening of security ties on the sidelines of G7
Recommendation
What do we know about the mysterious drones reported flying over New Jersey?
New Edition announces 2024 Las Vegas residency, teases new music: 'It makes sense'
New measures to curb migration to Germany agreed by Chancellor Scholz and state governors
Evan Ellingson, child star from 'My Sister's Keeper' and '24', dead at 35
The White House is cracking down on overdraft fees
Ex-gang leader to get date for murder trial stemming from 1996 killing of Tupac Shakur
Toyota, Ford, and Jeep among 2.1 million vehicles recalled: Check car recalls here
Can you make your bed every day? Company is offering $1000 if you can commit to the chore